Get Big Pivots

 

New Mexico Gov. Michelle Lujan Grisham was among those who helped snip the ribbon at the Taos Mesa Solar Array on June 3.

Altogether the cooperative now has 41 megawatts of solar capacity within its service territory in addition to 15 megawatts of battery storage.

This is sufficient to meet the daytime needs of the 7,500 homes within the service territory of Kit Carson in northern New Mexico.

Kit Carson set out to develop its solar capacity in 2002, long before solar was competitive. In 2016, though, directors as well as Luis Reyes Jr., the long-time chief executive, were clear about the future. They negotiated an exit fee of $37 million from wholesale provider Tri-State Generation and Transmission and realigned with a new wholesale provider, Guzman Energy.

Kit Carson is scheduled to make its final payment to Tri-State on June 30.

What is Kit Carson’s carbon mix? Reyes says he doesn’t know, and Guzman does not disclose that information.

 

Allen Best